Sangani Vala Stop Bridge
In Progress SH-87 (Anand–Khambhat Road)
Anand District · Vasad–Khambhat Stretch · Ch. 24+750
·
Sub-Divn: M/s Patel Construction Co. (Anand)
Work Value (Sanctioned)
₹ 6,75,00,000
Work Order Date
15-03-2025
Stipulated Completion
14-09-2026
Length / Spans
142 m · 4 Spans
Total Work Amount
₹ 6,75,00,000
Sanctioned · incl. all items
Total Bills Paid
₹ 4,52,78,500
5 running bills · last on 12-05-2026
Financial Progress
67.08%
Physical Progress
71.50%
Physical vs Financial Progress
Cumulative % at each running-bill milestone
Last financial update: 12-05-2026
5 days ago · RB #5
Physical Progress
Financial Progress
Financial lagging physical by 4.42% — typical for bill-cycle timing
Running Bills
Inline-editable · Sub Division Amount drives Financial Progress %
| RB No. | Bill Date | Sub Division Amount | Cumulative % | Status | |
|---|---|---|---|---|---|
| Totals → | |||||
Financial Progress Calculation
As of 12-05-2026 (RB #5)
Financial Progress %
=
Σ Sub Division Amount
÷
Total Work Amount
×
100
=
₹ 4,52,78,500
÷
₹ 6,75,00,000
×
100
=
67.08 %
Only the Sub Division Amount column contributes to financial progress.