MOCKUP v1.0 New Financial Details tab on Bridge Overview — running bills entry, financial vs physical progress chart, financial % calculation 22 Open Questions for Client Prepared 17-05-2026
Dashboard List of Bridges Sangani Vala Stop Bridge · Overview
Total Work Amount
₹ 6,75,00,000
Sanctioned · incl. all items
Total Bills Paid
₹ 4,52,78,500
5 running bills · last on 12-05-2026
Financial Progress
67.08%
Physical Progress
71.50%
Sub Division Amount is the contractor's measured value excluding Star Rate and Price Adjustment components — it is the figure used to compute Financial Progress against Total Work Amount.

Physical vs Financial Progress

Cumulative % at each running-bill milestone

Last financial update: 12-05-2026
5 days ago · RB #5
Physical Progress
Financial Progress
Financial lagging physical by 4.42% — typical for bill-cycle timing

Running Bills

Once added, entries are locked · Use Delete to remove · Sub Division Amount drives Financial Progress %

RB No. Bill Date Sub Division Amount Cumulative % Status
Totals →

Financial Progress Calculation

As of 12-05-2026 (RB #5)
Financial Progress % = Σ Sub Division Amount ÷ Total Work Amount × 100
= ₹ 4,52,78,500 ÷ ₹ 6,75,00,000 × 100 = 67.08 %
Only the Sub Division Amount column contributes to financial progress.