MOCKUP v1.1 v1.1 adds Project Cost Configuration (Sanctioned + COS/Excess + Revised + Revised Weightage) and a Planned vs Actual Cost Curve line chart on milestones & time Open Questions for Client Prepared 17-05-2026
Dashboard List of Bridges Sangani Vala Stop Bridge · Overview
Sanctioned Cost
₹ 6,75,00,000
Locked baseline · 100%
Revised Cost
₹ 7,15,00,000
+ ₹40,00,000 across 2 COS entries
Financial Progress
63.32%
Physical Progress
71.50%

Project Cost Configuration NEW

Captured from Edit Bridge → Financial Details section. Sanctioned Cost locks after first save. Adding a COS/Excess entry recalculates Revised Cost & component weightages.

Editable from Edit Bridge form
Locked

Saved on 22-07-2025 · cannot be edited (UI & API enforced)

Sequence Cost Amount Approval Letter
₹ 7,15,00,000
6,75,00,000 + 25,00,000 + 15,00,000
Always read-only · recomputed live as COS entries change

Recalc formula pending client confirmation — see Q4 in questions.html

Component Original Revised Δ
Sub Division Amount is the contractor's measured value excluding Star Rate and Price Adjustment components — it is the figure used to compute Financial Progress against Revised Project Cost.

Physical vs Financial Progress

Cumulative % at each running-bill milestone

Last financial update: 12-05-2026
5 days ago · RB #5
Physical Progress
Financial Progress
Financial lagging physical by 4.42% — typical for bill-cycle timing

Planned vs Actual Cost Curve NEW

Cumulative ₹ over project timeline · Planned milestones at 25% / 50% / 75% / 100% (months 3 / 6 / 9 / 12) · Actuals from running bills

Project started 15-07-2025
Time limit 12 months · ends 15-07-2026
Planned (Revised Cost curve)
Actual (Σ Sub Division)
Planned milestone
Running bill (actual)

Running Bills

Once added, entries are locked · Use Delete to remove · Sub Division Amount drives Financial Progress %

RB No. Bill Date Sub Division Amount Cumulative % Status
Totals →

Financial Progress Calculation

As of 12-05-2026 (RB #5)
Financial Progress % = Σ Sub Division Amount ÷ Revised Project Cost × 100
= ₹ 4,52,78,500 ÷ ₹ 7,15,00,000 × 100 = 63.32 %
Only the Sub Division Amount column contributes to financial progress.